Back to glossary

Planning, Contracts, and Permits

Terms tied to scope, pricing, legal constraints, and job setup before construction begins.

42 terms

Allowance
An allowance is a budget placeholder for an item you have not selected yet, like tile or fixtures.
Planning, Contracts, and Permits
Arbitration
Arbitration is a method of resolving contract disputes outside of court, where a neutral third party (the arbitrator) makes a binding decision.
Planning, Contracts, and Permits
As-built
As-built documents show what was actually installed and where, after changes during construction.
Planning, Contracts, and Permits
Broom Clean
Broom clean is a contract standard meaning the builder will remove all debris, sweep the floors, and leave the property relatively tidy at turnover.
Planning, Contracts, and Permits
Builder's Risk Insurance
Builder's Risk Insurance is a specialized property insurance that covers the home and materials during construction against damage like fire, wind, or theft.
Planning, Contracts, and Permits
Certificate of insurance (COI)
A certificate of insurance is a document that shows the builder has active insurance, usually general liability and workers comp.
Planning, Contracts, and Permits
Certificate of Occupancy (CO)
A Certificate of Occupancy is an official document issued by the local government verifying that a building complies with building codes and is safe to live in.
Planning, Contracts, and Permits
Change order
A change order is a written agreement that changes the scope, cost, or schedule after work starts.
Planning, Contracts, and Permits
Change order markup
Change order markup is the percentage the builder adds to cover overhead and profit on change work.
Planning, Contracts, and Permits
Contingency
Contingency is extra money and time set aside for unknowns, especially in remodels.
Planning, Contracts, and Permits
Cost-Plus Contract
A cost-plus contract is an agreement where the homeowner pays the actual cost of materials and labor, plus a fixed percentage or fee for the builder's overhead and profit.
Planning, Contracts, and Permits
Data plate
A data plate is the label on equipment that shows model number, serial number, manufacture date, and specifications.
Planning, Contracts, and Permits
Draw schedule
A draw schedule is the plan for when payments happen, usually tied to milestones.
Planning, Contracts, and Permits
Easement
An easement is a legal right that allows someone other than the property owner to use a specific portion of the property.
Planning, Contracts, and Permits
Escalation clause
An escalation clause is a contract provision that allows the builder to increase the price if the cost of materials (like lumber or copper) spikes unexpectedly during construction.
Planning, Contracts, and Permits
Exclusions
Exclusions are items and tasks the contract says the builder will not provide.
Planning, Contracts, and Permits
Excusable delay
An excusable delay is a delay caused by events outside the builder's control, giving them an extension of time without penalty.
Planning, Contracts, and Permits
Final walkthrough
A final walkthrough is an inspection near the end of a project to identify punch list items before you accept the work as complete.
Planning, Contracts, and Permits
Fixed-Price Contract
A fixed-price (or stipulated sum) contract is an agreement where the builder agrees to complete the project for a single, guaranteed total price.
Planning, Contracts, and Permits
Force majeure
Force majeure is a contract clause that excuses a party from fulfilling their obligations due to an extraordinary, unforeseeable event beyond their control (an 'Act of God').
Planning, Contracts, and Permits
General Conditions
General conditions are the indirect 'soft costs' of a construction project, such as portable toilets, dumpsters, site supervision, temporary power, and cleanup.
Planning, Contracts, and Permits
GMP (Guaranteed Maximum Price)
A GMP is a contract structure that sets a maximum price, with rules for what happens if costs go above or below.
Planning, Contracts, and Permits
Inclusions
Inclusions are items and tasks the contract says the builder will provide.
Planning, Contracts, and Permits
Indemnification
Indemnification is a contract clause where one party agrees to financially protect (or 'hold harmless') the other party against specific third-party claims or lawsuits.
Planning, Contracts, and Permits
Inspection
An inspection is a checkpoint where an inspector verifies work meets code before it gets covered up.
Planning, Contracts, and Permits
Lien waiver
A lien waiver is a document that says a contractor or supplier has been paid and will not file a lien for that payment.
Planning, Contracts, and Permits
Liquidated damages
Liquidated damages are a pre-agreed daily or weekly financial penalty the builder pays if the project is delayed past the contracted completion date.
Planning, Contracts, and Permits
Mechanic's lien
A mechanic's lien is a legal claim placed on your property by a contractor, subcontractor, or supplier who hasn't been paid for their work or materials.
Planning, Contracts, and Permits
Milestone draw
A milestone draw is a scheduled payment made to the builder when a specific, verifiable stage of construction is completed.
Planning, Contracts, and Permits
Notice to proceed
A notice to proceed is a formal written authorization from the owner telling the builder to start work.
Planning, Contracts, and Permits
Packaging or installation certificate
A packaging or installation certificate is the document included with an appliance that records the installation date and is needed to activate the warranty.
Planning, Contracts, and Permits
Permit
A permit is official approval to do certain work, usually tied to safety rules and inspections.
Planning, Contracts, and Permits
Pre-drywall walkthrough
A pre-drywall walkthrough is a scheduled visit to inspect framing, wiring, plumbing, and insulation before drywall covers everything up.
Planning, Contracts, and Permits
Punch list
A punch list is a final list of small fixes and finish details before you call the job complete.
Planning, Contracts, and Permits
Retainage
Retainage is money held back from each payment until the end of the job.
Planning, Contracts, and Permits
RFI (Request for Information)
An RFI is a formal question used to clarify plans and details before work continues.
Planning, Contracts, and Permits
Right to cure
A right to cure clause gives the builder a specific amount of time to fix defective work or a breach of contract before you can terminate them or hire someone else.
Planning, Contracts, and Permits
Schedule of values (SOV)
A schedule of values is a list that breaks the contract price into line items like framing, plumbing, electrical, and finishes.
Planning, Contracts, and Permits
Scope of work
Scope of work is the written list of what the builder will do and what the builder will deliver.
Planning, Contracts, and Permits
Substantial completion
Substantial completion is the point when the home is usable for its intended purpose, even if small items remain.
Planning, Contracts, and Permits
Turnkey
A turnkey contract means the builder is responsible for delivering a completely finished home, ready to use—you just 'turn the key' and walk in.
Planning, Contracts, and Permits
Warranty
A warranty is the builder’s promise to fix certain issues for a set time after completion.
Planning, Contracts, and Permits

Most people do not just struggle with terms. They struggle with the decisions tied to them.

See how HouseChalk helps with the decisions behind terms like this